For hyperscale data center developers, the challenge is no longer theoretical. Utilities in many regions cannot deliver 24/7 firm power, with waits as long as three to six years, forcing developers to either delay projects or rely on costly, standalone power solutions that lock in long-term self-generation and cause friction in communities.
Now regulators, utilities and large load facilities recognize that the solution is flexible, dispatchable generation co-located with large loads. These systems allow large loads to operate at full capacity by self-supplying the load during grid-constrained hours. This defers the need for immediate systemwide resource additions or transmission and substation upgrades, easing rate pressure while bolstering system reliability.
Recent modeling from Camus, Encoord and Princeton University’s ZERO Lab demonstrates the effectiveness of this approach. The research found that a 500 MW data center with flexible grid connection and on-site generation capacity can achieve full operation “three to five years faster than traditional interconnection processes,” and can also reduce grid costs by $78 million per GW of demand. For large data centers, this acceleration can realize tens of millions of dollars per month in revenue.
Flexible, co-located generation enables large-load connections via interim service. Onsite power covers demand during grid constraints and later transitions to firm service. (Image from Commissioner David Rosner’s concurrence in Dec. 18 Order.)
As data center developers prioritize time-to-power, onsite generation developers have emerged as critical execution partners, designing, permitting, financing and operating flexible generation that large loads can rely on for power today and utilities can access tomorrow.
Aligning large load needs with utility planning
Large load C&I customers, such as hyperscale data centers, operate in a fast, innovation-driven environment, markedly different from utilities, which are often slowed by the need to comply with a myriad of complex state and federal regulations. Historically, data center grid interconnection requests to utilities were predictable and manageable. However, as hyperscalers and other large loads began to make exponentially larger load interconnection requests across regions, utilities began to say “no” for the first time. The two sides quickly realized it was imperative that they better understand each other's businesses.
Some onsite generation developers have worked closely with utilities and data center developers for years. They understand the challenges that both face and deliver a technical solution that solves them. As a result, companies like Enchanted Rock are increasingly called upon to serve as facilitator in two ways.
- Grid access strategist: Utilities require demand flexibility to serve large loads more quickly. Hyperscalers need that flexibility delivered rapidly, reliably and at the lowest possible total cost. Distributed energy resource developers have the technical expertise to align both by shaping utility-scale onsite generation to fit the needs of both parties, while benefiting the grid, local community and ratepayers
- Infrastructure provider: Developers deploy dispatchable generation, smart controls and demand response capabilities that meet prime-power needs today and transitions to backup and grid-support roles once utility service arrives, eliminating redundant spend on diesel backup and avoiding permanent self-generation lock-in.
As a result, the relationship between large loads and onsite generation is shifting from one-off projects to portfolio-level deployment. For hyperscalers and data center developers building dozens of facilities across constrained regions, flexible onsite generation becomes a repeatable, standardized pathway to power, lower total cost of ownership and consistent reliability.
Flexible onsite generation has the potential to help large loads advance in utility interconnection queues by being able to accept interruptible service until grid upgrades are completed, allowing facilities to not only commission faster but monetize capacity years earlier than traditional timelines.
A new interconnection model emerges
Solving these grid issues doesn’t just impact business leaders, U.S. economic competitiveness could hang in the balance, as well as the reliability and affordability of electricity for millions of customers. With any challenge of this magnitude, new rules become essential to navigate the changing landscape.
The Federal Energy Regulatory Commission (FERC) has taken an important first step—one that could enable a change in utility interconnection approaches from “build then connect” to “connect while building.” In FERC Order EL25-49, the commission directed the PJM Interconnection regional transmission organization (RTO) to establish clear, transparent pathways for large loads to pull power from the grid, including through Network Integration Transmission Service (NITS) or non-firm contract demand transmission service.
As James Huang, Enchanted Rock director of wholesale markets policy, wrote in January, these frameworks for service “enable immediate large load interconnection on a non-firm basis, with conversion to firm service once required grid upgrades are completed.” In practice, these frameworks allow data centers to operate at scale immediately, using onsite generation to manage grid constraints, and then transition seamlessly to firm service as grid infrastructure is built.
PJM will be the first to implement these transmission service innovations, thus enabling quicker interconnection of flexible demand data centers, but ERCOT, SPP and several vertically integrated utilities are taking a similar approach.
For large load facilities like hyperscale data centers, they need a model like Enchanted Rock’s that delivers what traditional approaches cannot: faster time-to-power, lower total cost and a permitting-friendly solution with low local emissions, no water use, quiet operation and minimal visual impact. As utilities and regulators embrace flexibility, onsite generation is no longer just a resilience tool, it is becoming the fastest, most economical path to grid access for large loads.