Regulation & Policy
-
Fossil fuel generation pipeline rebounds while new clean generation slows: EDF
However, “rising gas turbine costs and supply shortages are already making new gas plants more expensive and slower to build,” David Villagrana, EDF’s lead counsel for clean energy tax solutions, told Utility Dive.
By Diana DiGangi • Oct. 14, 2026 -
PJM plans to study SoftBank’s Ohio AI project under state agreement approach
The project, dubbed “Flagship,” includes 765-kV transmission lines to be built by AEP Ohio, roughly 10 GW in data center load and about 10.2 GW in gas-fired generation.
By Ethan Howland • Oct. 14, 2026 -
Explore the Trendline➔
Brandon Bell via Getty Images
TrendlineData Centers and the US Grid
A look at how data centers are affecting the U.S. grid today and how new technologies and rate structures could affect that trajectory in the years to come.
By Utility Dive staff -
FERC approves Duke large load transmission rules despite cost-shift concerns
Commissioner David Rosner said that Duke Energy Carolinas’ proposal offers “meaningful, if imperfect, new protections,” adding that consumer protections are “inadequate across the country” and FERC may need to take further action.
By Ethan Howland • Oct. 13, 2026 -
Dominion-NextEra merger hearing focused on rates, data centers
“When Dominion was asked about the [Virginia Clean Economy Act], its executive vice president told the commission, ‘I am still your throat to choke,’ and that was a shocking thing for me to hear as a legislator,” said Virginia Del. Irene Shin, D.
By Diana DiGangi • Oct. 12, 2026 -
FERC rejects most of PJM’s large load interconnection plan
The PJM Interconnection’s plan for curtailing large loads that don’t have matching new generation intrudes on state jurisdiction and appears to be discriminatory, the Federal Energy Regulatory Commission said.
By Ethan Howland • Oct. 12, 2026 -
Sponsored by eSmart Systems
Beyond the checklist: How connected asset data is reshaping grid risk
Regulators are raising the bar on what an inspection has to prove.
By Donald McPhail • Oct. 12, 2026 -
PJM approves fast-track interconnection for 2.1 GW from Engie, LS Power
The grid operator expects Engie’s two storage projects totaling nearly 1.7 GW and LS Power’s 455-MW gas-fired uprate will be online by mid-2029.
By Ethan Howland • Oct. 9, 2026 -
US electric, gas utility rate requests spike to $4.5B in Q3: PowerLines
The cumulative value of third quarter rate requests more than doubled from the third quarter of 2025, according to a report from the advocacy group.
By Robert Walton • Oct. 9, 2026 -
Power system plans to meet large-load demand miss near-term solutions: analysts
Major work by regional planners is focused on flexible access to existing transmission. Some say greater emphasis on advanced transmission technologies can quickly and cost-effectively create room for new large loads.
By Herman K. Trabish • Oct. 8, 2026 -
DOE presses PJM on ratepayer protections from large load costs
“A capability to continuously track whether a project enters into service ... or is delayed, reduced, or cancelled, can help assign costs for new generation to the customers responsible for those investments,” the DOE said in a rare filing at FERC.
By Ethan Howland • Updated Oct. 8, 2026 -
Virginia regulators approve Dominion’s fuel cost recovery, securitization
The Virginia State Corporation Commission approved fuel cost securitization for the second time since 2023, adding additional interest costs for customers.
By Charles Paullin • Oct. 7, 2026 -
Virginia Lt. Gov. Hashmi opposes NextEra-Dominion merger as public hearings begin
“We are disappointed by the lieutenant governor’s decision and respectfully disagree with it,” Neil Nissan, a spokesperson for NextEra Energy, told Utility Dive. State regulators are set to hold their first local hearing on the case Wednesday.
By Diana DiGangi • Oct. 7, 2026 -
Top electric power sector and utility conferences in 2027
Utility Dive’s curated list of notable events where energy professionals will gather to exchange ideas, demonstrate novel approaches and network for a new era of grid modernization.
By Meris Lutz • Oct. 6, 2026 -
Opinion
A new VPP framework can center the energy transition in Illinois around customers: ComEd VP
Commonwealth Edison will file a virtual power plant framework by the end of 2027 that looks beyond batteries, writes Andrew Plenge, vice president of strategy and energy policy at the Illinois utility.
By Andrew Plenge • Oct. 6, 2026 -
States, renewable developers back MISO’s accelerated interconnection queue plan
“This approach can materially accelerate the processing of legacy queue cycles while preserving MISO’s responsibility to identify and address reliability concerns,” the Organization of MISO States said.
By Ethan Howland • Oct. 6, 2026 -
Virginia hearing examiner tells Dominion to release memo on FPL investigation
Dominion said the memo wasn’t relevant to its merger with NextEra Energy, but Clean Virginia, a customer advocacy group, said it speaks to the governance “fitness” of the potential combined company.
By Charles Paullin • Oct. 5, 2026 -
MISO proposes fast-track large load, generation study process
The 120-day study process would be available for loads larger than 200 MW and new generation that is in the same local resource zone, which generally consists of individual states.
By Ethan Howland • Oct. 5, 2026 -
Cities, states sue EPA over power plant emissions rollback
Chicago, Denver and New York City joined multistate lawsuits challenging the agency’s move to end greenhouse gas emissions standards and failure to enforce requirements on existing gas-fired plants.
By Robyn Griggs Lawrence • Oct. 2, 2026 -
The image by Steven Baltakatei Sandoval is licensed under CC BY-SA 4.0
FERC rejects TransAlta 202(c) cost-recovery plan for Centralia unit
Only utilities in the Northwest should pay the nearly $20 million in expenses for a 90-day order covering the Centralia unit, and despite the unit’s lack of output, payment is due, the agency said.
By Ethan Howland • Oct. 2, 2026 -
FERC chair slams PJM ‘mess’ as country’s largest grid operator delays power auction
PJM had planned to accept offers for backstop power supplies from Sept. 30 through Oct. 21 after falling short of its reserve margin targets. But FERC only partially approved its plan, zeroing in on cost allocation concerns.
By Ethan Howland • Sept. 30, 2026 -
Lawsuit alleges USDA illegally slashed rural solar development program
Internal emails show a department administrator stating “let’s let the comms shop find . . . the rationale behind their statistics” when asked to substantiate anti-solar claims underpinning the policy changes, the complaint says.
By Ethan Howland • Sept. 29, 2026 -
Data center backup power contributes to health risks: report
Federal regulatory actions are allowing on-site generators at data centers and other power plants to release dangerous emissions with fewer checks, according to the Environmental Protection Network.
By Robert Freedman • Sept. 28, 2026 -
SPP’s ‘stop-gap’ resource adequacy plan for Western balancing area panned at FERC
The Federal Energy Regulatory Commission should reject the proposal, in part because it would stifle markets, the Southwest Power Pool’s market monitor said.
By Ethan Howland • Sept. 28, 2026 -
Second federal judge overturns $7B Solar for All cancellation
The decision in a suit brought by Harris County, Texas, follows a similar ruling last week. A Harris County judge called it “a really important victory for energy resilience.”
By Robyn Griggs Lawrence • Sept. 25, 2026 -
FERC rejects Oklo complaint seeking to reinstate project to PJM’s interconnection study cycle
The decision affects a 750-MW, mixed technology project in Virginia, which Oklo said would be delayed by at least 18 months if it misses the current interconnection cycle.
By Ethan Howland • Sept. 25, 2026